Location:Sy. No. 31, Chikkanagmangala
village,
Sarjapura Hobli, Anekal
taluk, Bengaluru Urban District 560099
Capacity:350 TPD wet waste
Status:Functional (receiving 279 TPD)
Date
of
Commencement:18.11.2015
Waste
Processed:4,57,521MT
Legislative
Assembly
Constituency:Anekal
Mode
of
Operation:Through Joint
Commissioner (South), BBMP
Location:Sy. No. 75, Doddabidarkallu village,
Yeshwanthpura, Bengaluru.
Capacity:150 TPD wet waste.
Status:Functional (Receiving 81 TPD)
Date
of
Commencement:11.09.2015
Waste
Processed:4,57,521MT
Legislative
Assembly
Constituency:Anekal
Mode
of
Operation:Through Joint
Commissioner (Dasarahalli), BBMP
Legislative
Assembly Constituency: Yeshwanthpura
Proposed for
Waste to Energy plant by M/s. Indium Company Bangalore.
Location:Sy. No. 85 Kannahalli village,
Seegehalli cross Magadi
main road Bengaluru.
Capacity:350 TPD wet waste.
Status: Functional (Receiving 254 TPD)
Date
of
Commencement:31.07.2015
Waste
Processed:3,02,725
MT
Legislative
Assembly
Constituency:Yeshwanthpura
Mode
of
Operation:Through Joint
Commissioner (West),
BBMP
Plant has been
handed over on 18.01.2021 to M/s Saateram
Alternative Fuel & energy Pvt Ltd for establishment of 14.5 MW
Waste to Energy plant from 1000 TPD mixed waste.
Location:Sy. No. 39 & 40, Haralakunte
village,
Madiwala Post, Hosur road Bengaluru.
Capacity:350 TPD wet waste.
Status:Functioning (Receiving 194 TPD)
Date
of
Commencement:15.07.2017
(Upgraded) Plant Existing since 1975
Waste
Processed:2,52,472
MT
Legislative
Assembly
Constituency:Bommanahalli
Mode
of
Operation:Through MD-
KCDC / JC (Bommanahalli), BBMP
Location:Sy No.16A and 21/1, CA site No.05,
BBMP,
W- 198, Banashankari 6th stage, Bengaluru-560109.
Capacity:150 TPD wet waste.
Status:Functioning (Receiving 86 TPD)
Waste
Processed:73,326
MT
Legislative
Assembly
Constituency:Yeshwanthpura
Date
of
Commencement:15.07.2017
(Upgraded) Plant Existing since 1975
Mode
of
Operation:Through Joint
Commissioner (East), BBMP
Location:Sy No. 48, Seegehalli village,
Yeshwanthapura Hobli, Bengaluru north Taluk, Bengaluru Urban
District.
Capacity:120 TPD wet waste
Status:Functioning (Receiving 111 TPD)
Date
of
Commencement:08.08.2015
Date
of
Closure:28.05.2020 plant
is recommenced on 14.07.2023
Waste
Processed:78,261MT
Legislative
Assembly
Constituency:Yeshwanthpura
Mode
of
Operation:Through Joint
Commissioner (RR Nagar), BBMP
Reason for
stoppage of plant: A
Residential school at Chennenahalli have objected to recommence
the plant due to odour generation, which affects the health of
students.
Location:Sy. No. 143, Kumbalgudu, Kengeri
Hobli,
Bengaluru South Taluk, Bengaluru-74
Capacity:150 TPD wet waste
Status:Functioning (Receiving 41 TPD)
Date
of
Commencement:03.09.2015
Waste
Processed:43454MT
Legislative
Assembly
Constituency:Yeshwanthpura
Mode
of
Operation:Through Joint
Commissioner (Mahadevapura), BBMP
Reason for
stoppage of plant: Due to
local agitation from 22.01.2023